Filed possession date passed about 7 years ago
Its filed possession date was 2018-10-05 and it was 97% booked, so it may well be delivered by now — but the recorded status (“On-Going Project”) is from an older snapshot and hasn't been updated. Please confirm the current, live status on the official MahaRERA portal.
Check the live status on MahaRERA ↗✓
No complaints, court cases or revocation in the public record
Based on the government snapshot as of 2021-07-23.
Project at a glance
TypeResidential
Homes33
Sanctioned floors42
Possession (filed)2018-10-05
Booked97%