MahaRERA project record

Tulsi Developers

by Tulsi Developers · Nanded · RERA P51100005078

Public MahaRERA snapshot · as of 2020-01-18
!
Filed possession date passed about 8 years ago

Its filed possession date was 2018-03-18 and it was 91% booked, so it may well be delivered by now — but the recorded status (“On-Going Project”) is from an older snapshot and hasn't been updated. Please confirm the current, live status on the official MahaRERA portal.

Check the live status on MahaRERA ↗
No complaints, court cases or revocation in the public record

Based on the government snapshot as of 2020-01-18.

Project at a glance

TypeResidential
Homes32
Sanctioned floors10
Possession (filed)2018-03-18
Booked91%
Open the full report — scores, map & evidenceSee Tulsi Developers's full portfolio & risk record

Compiled from the public MahaRERA record. Gharoba is independent, takes no money from any builder, and is not affiliated with any government body. This is decision-support, not legal or financial advice — always confirm the current status on the official MahaRERA portal before you decide.