MahaRERA project record

SHREE SIDDHI VINAYAK APPARTMENT

by RIDDHI SIDDI DEVELOPERS · Nashik · RERA P51600004980

Public MahaRERA snapshot · as of 2021-09-01
!
Filed possession date passed about 7 years ago

Its filed possession date was 2018-12-31 and it was 92% booked, so it may well be delivered by now — but the recorded status (“On-Going Project”) is from an older snapshot and hasn't been updated. Please confirm the current, live status on the official MahaRERA portal.

Check the live status on MahaRERA ↗
No complaints, court cases or revocation in the public record

Based on the government snapshot as of 2021-09-01.

Project at a glance

TypeResidential
Homes26
Sanctioned floors5
Possession (filed)2018-12-31
Booked92%