MahaRERA project record

THARWANI ARIANA PHASE III

by ANIL HARDASMAL THARWANI · Thane · RERA P51700006728

Public MahaRERA snapshot · as of 2023-07-13
!
Filed possession date passed about 3 years ago

Its filed possession date was 2023-04-30, so it may well be delivered by now — but the recorded status (“On-Going Project”) is from an older snapshot and hasn't been updated. Please confirm the current, live status on the official MahaRERA portal.

Check the live status on MahaRERA ↗
!
What the public record flags
  • 2 court cases on record

A complaint or case does not by itself prove wrongdoing — many are minor or already resolved. Confirm the live status on MahaRERA.

Project at a glance

TypeResidential
Homes240
Sanctioned floors40
Possession (filed)2023-04-30
Booked85%