MahaRERA project record

SAI KANISHK PHASE I

by Om Sai Infra & Om Sai Group · Thane · RERA P51700006847

Public MahaRERA snapshot · as of 2019-10-11
!
Filed possession date passed about 8 years ago

Its filed possession date was 2018-05-31, so it may well be delivered by now — but the recorded status (“On-Going Project”) is from an older snapshot and hasn't been updated. Please confirm the current, live status on the official MahaRERA portal.

Check the live status on MahaRERA ↗
!
What the public record flags
  • 10 buyer complaints on record

A complaint or case does not by itself prove wrongdoing — many are minor or already resolved. Confirm the live status on MahaRERA.

Project at a glance

TypeResidential
Homes84
Sanctioned floors24
Possession (filed)2018-05-31
Booked83%
Open the full report — scores, map & evidenceSee Om Sai Infra & Om Sai Group's full portfolio & risk record