MahaRERA project record

MUKATA LAKE CITY

by KANAK REALTORS · Thane · RERA P51700008734

Public MahaRERA snapshot · as of 2024-03-11
!
Filed possession date passed about 5 years ago

Its filed possession date was 2020-12-29, so it may well be delivered by now — but the recorded status (“On-Going Project”) is from an older snapshot and hasn't been updated. Please confirm the current, live status on the official MahaRERA portal.

Check the live status on MahaRERA ↗
No complaints, court cases or revocation in the public record

Based on the government snapshot as of 2024-03-11.

Project at a glance

TypeResidential
Homes42
Sanctioned floors7
Possession (filed)2020-12-29
Booked83%
Open the full report — scores, map & evidenceSee KANAK REALTORS's full portfolio & risk record

Compiled from the public MahaRERA record. Gharoba is independent, takes no money from any builder, and is not affiliated with any government body. This is decision-support, not legal or financial advice — always confirm the current status on the official MahaRERA portal before you decide.