MahaRERA project record

REDEVELOPMENT OF MALAD RAJHANS CHSL

by PRANAV CONSTRUCTIONS LIMITED · Mumbai Suburban · RERA P51800002196

Public MahaRERA snapshot · as of 2021-08-30
!
Filed possession date passed about 7 years ago

Its filed possession date was 2019-03-31 and it was 98% booked, so it may well be delivered by now — but the recorded status (“On-Going Project”) is from an older snapshot and hasn't been updated. Please confirm the current, live status on the official MahaRERA portal.

Check the live status on MahaRERA ↗
No complaints, court cases or revocation in the public record

Based on the government snapshot as of 2021-08-30.

Project at a glance

TypeResidential
Homes55
Sanctioned floors21
Possession (filed)2019-03-31
Booked98%
Open the full report — scores, map & evidenceSee PRANAV CONSTRUCTIONS LIMITED's full portfolio & risk record