MahaRERA project record

DP STAR TRILOK

by DP BUILDHOMES LLP · Mumbai Suburban · RERA P51800003937

Public MahaRERA snapshot · as of 2023-11-28
!
Filed possession date passed about 2 years ago

Its filed possession date was 2023-12-14 and it was 95% booked, so it may well be delivered by now — but the recorded status (“On-Going Project”) is from an older snapshot and hasn't been updated. Please confirm the current, live status on the official MahaRERA portal.

Check the live status on MahaRERA ↗
No complaints, court cases or revocation in the public record

Based on the government snapshot as of 2023-11-28.

Project at a glance

TypeResidential
Homes84
Sanctioned floors21
Possession (filed)2023-12-14
Booked95%
Open the full report — scores, map & evidenceSee DP BUILDHOMES LLP's full portfolio & risk record

Compiled from the public MahaRERA record. Gharoba is independent, takes no money from any builder, and is not affiliated with any government body. This is decision-support, not legal or financial advice — always confirm the current status on the official MahaRERA portal before you decide.