Filed possession date passed about 2 years ago

Its filed possession date was 2024-03-31, so it may well be delivered by now — but the recorded status (“New Project”) is from an older snapshot and hasn't been updated. Please confirm the current, live status on the official MahaRERA portal.

Check the live status on MahaRERA ↗
No complaints, court cases or revocation in the public record

Based on the government snapshot as of 2024-03-06.

Project at a glance

TypeResidential
Homes7
Sanctioned floors11
Possession (filed)2024-03-31
Booked14%