MahaRERA project record
TULSI SONATA
Public MahaRERA snapshot · as of 2023-03-01
!
Filed possession date passed about 7 years ago
Its filed possession date was 2019-04-30, so it may well be delivered by now — but the recorded status (“On-Going Project”) is from an older snapshot and hasn't been updated. Please confirm the current, live status on the official MahaRERA portal.
Check the live status on MahaRERA ↗✓
No complaints, court cases or revocation in the public record
Based on the government snapshot as of 2023-03-01.
Project at a glance
TypeResidential
Homes106
Sanctioned floors20
Possession (filed)2019-04-30
Booked79%
Compiled from the public MahaRERA record. Gharoba is independent, takes no money from any builder, and is not affiliated with any government body. This is decision-support, not legal or financial advice — always confirm the current status on the official MahaRERA portal before you decide.