MahaRERA project record

Disha Heights

by Dinesh Prabhakar Baravkar · Pune · RERA P52100009125

Public MahaRERA snapshot · as of 2019-07-01
!
Filed possession date passed about 7 years ago

Its filed possession date was 2018-12-30, so it may well be delivered by now — but the recorded status (“On-Going Project”) is from an older snapshot and hasn't been updated. Please confirm the current, live status on the official MahaRERA portal.

Check the live status on MahaRERA ↗
No complaints, court cases or revocation in the public record

Based on the government snapshot as of 2019-07-01.

Project at a glance

TypeResidential
Homes32
Sanctioned floors5
Possession (filed)2018-12-30
Booked38%
Open the full report — scores, map & evidenceSee Dinesh Prabhakar Baravkar's full portfolio & risk record

Compiled from the public MahaRERA record. Gharoba is independent, takes no money from any builder, and is not affiliated with any government body. This is decision-support, not legal or financial advice — always confirm the current status on the official MahaRERA portal before you decide.