MahaRERA project record
MY HOME WAKAD
Public MahaRERA snapshot · as of 2023-12-23
i
Status: New Project
As recorded in the public MahaRERA snapshot.
!
What the public record flags
- 1 court case on record
- 1 buyer complaint on record
A complaint or case does not by itself prove wrongdoing — many are minor or already resolved. Confirm the live status on MahaRERA.
Project at a glance
TypeResidential
Homes210
Sanctioned floors29
Possession (filed)2027-06-30
Booked44%
Open the full report — scores, map & evidenceSee SAMRUDDHI PROPERTIES's full portfolio & risk record
Compiled from the public MahaRERA record. Gharoba is independent, takes no money from any builder, and is not affiliated with any government body. This is decision-support, not legal or financial advice — always confirm the current status on the official MahaRERA portal before you decide.