MahaRERA project record

KSP RESIDENCY

by KRISHNAT SHAHU POWAR · Ratnagiri · RERA P52800012180

Public MahaRERA snapshot · as of 2022-04-12
!
Filed possession date passed about 6 years ago

Its filed possession date was 2019-12-26, so it may well be delivered by now — but the recorded status (“On-Going Project”) is from an older snapshot and hasn't been updated. Please confirm the current, live status on the official MahaRERA portal.

Check the live status on MahaRERA ↗
No complaints, court cases or revocation in the public record

Based on the government snapshot as of 2022-04-12.

Project at a glance

TypeOthers
Homes61
Sanctioned floors12
Possession (filed)2019-12-26
Booked67%
Open the full report — scores, map & evidenceSee KRISHNAT SHAHU POWAR's full portfolio & risk record